A closure-based in-situ chemical oxidation (ISCO) program was implemented at an operational power generation plant in Northwestern Alberta to remediate F2 and vinyl chloride contamination in 300 m³ of impacted soil. Site constraints, including existing infrastructure and a lack of groundwater, required a 0.75-meter injection radius for increased contact certainty. Over five days, 37 injection points were advanced, delivering 32,800 liters of 12% EHP (enhanced hydrogen peroxide) using TRIUM’s ChemOx® process. The treatment successfully met applicable soil quality guidelines within a short timeframe, with no disruptions to facility operations.
Historical operations in the area had impacted the soil. Infrastructure currently in place limiting the remedial strategies available. Soil comprised of sandy loam with little to no moisture. Groundwater was present deeper than the zone of impacts.
In-situ chemical oxidation (ISCO) program based on 0.75 meter injection radius of influence to increase contact certainty between the oxidant and the contaminants due to lack of groundwater. Injections were conducted using drive-points to target various depth intervals within each injection point. Due to current operations, the program demanded that injections could not conflict with day-to-day operations of the facility.
Over 5 days, advanced 37 injection points, and injected 32,800 litres of blended 12% EHP (enhanced hydrogen peroxide) oxidant. Blending is site specific following TRIUM’s ChemOx® process.
An in-situ chemical oxidation (ISCO) remediation was conducted at a former wellsite sump in Barrhead, Alberta to address BTEX, F1, and F2 contamination in 645 m³ of impacted soil and 3,000 m³ of impacted groundwater. Due to shallow groundwater and a saturated silty sand lithology, excavation was limited, requiring targeted in-situ treatment. A 0.75-meter injection radius was used for soil treatment via 40 injection points, delivering 28,000 liters of 10-15% MFR (modified Fenton’s reagent) over five days, while groundwater remediation involved 13 wells, injecting 60,000 liters over two events spanning 20 days. Using TRIUM’s TriOx process, the project achieved a >90% contaminant reduction, meeting regulatory guidelines within a short treatment timeframe.
An in-situ chemical oxidation (ISCO) remediation was conducted at a residential property in North Vancouver to address petroleum hydrocarbons (LEPH), phenanthrene, and pyrene contamination in 200 m³ of impacted soil and groundwater following a heating oil UST leak that migrated under the building foundation, causing vapour intrusion and free product in property sumps. A 2.5-meter injection radius was used for targeted treatments within the basement and exterior property foundation, utilizing directional injections and drive-points to reach both saturated and unsaturated zones. TRIUM leveraged the property’s sump system to artificially raise the groundwater level, creating a fully saturated treatment zone. Over seven days, 24 basement injections and 3 exterior injections delivered 20,104 litres of sodium persulfate, blended using TRIUM’s TriOx process with specialized activation products. The treatment successfully met regulatory soil, groundwater, and vapour guidelines, required only six weeks for completion, and allowed the property owner to safely return home with minimal disturbance.