Case Study:

Wellsite Sump Remediation in Barrhead, AB: In-Situ Chemical Oxidation Success

Barrhead, Alberta In-Situ Chemical Oxidation

An in-situ chemical oxidation (ISCO) remediation was conducted at a former wellsite sump in Barrhead, Alberta to address BTEX, F1, and F2 contamination in 645 m³ of impacted soil and 3,000 m³ of impacted groundwater. Due to shallow groundwater and a saturated silty sand lithology, excavation was limited, requiring targeted in-situ treatment. A 0.75-meter injection radius was used for soil treatment via 40 injection points, delivering 28,000 liters of 10-15% MFR (modified Fenton’s reagent) over five days, while groundwater remediation involved 13 wells, injecting 60,000 liters over two events spanning 20 days. Using TRIUM’s TriOx process, the project achieved a >90% contaminant reduction, meeting regulatory guidelines within a short treatment timeframe.

Project Details:

Location:

Barrhead, Alberta

Site:

Former Wellsite Sump

Date:

2020
to
to
2020
Present

Contaminant of Concern:

BTEX, F1, F2

Impacted Media and Volume:

645 m3 impacted soil and 3,000 m3 impacted groundwater

Project Tasks:

Remediation Program Design, Blending, and Field applications

The Problem:

Former admixed drilling sump at an abandoned wellsite. Surficial soil impacts were excavated and removed from Site. Shallow groundwater limited excavation and required in-situ treatment method for remaining soil impacts and groundwater impacts. Lithology of the target treatment zone is saturated silty sand, creating a pathway for contaminant migration.

The Approach:

In-situ chemical oxidation (ISCO) program based on treatment of soils using drive points on a 0.75 meter injection radius of influence to increase contact certainty between the oxidant and contaminants due to unsaturated soils. Groundwater injections were completed using 13 injection wells targeting the saturated intervals. Injections were completed in the fall and winter so as to have a frost cap in winter.

The soil treatment program was conducted over 5 days with the advancement of 40 injection points and 28,000 litres of blended 10-15% MFR (modified fentons reagent) oxidant injected. The groundwater treatment program was conducted over 2 events for a total of 20 days and injection in 13 injection points and 60,000 litres of blended 10-15% MFR (modified fentons reagent) oxidant injected. Blending is site specific following TRIUM’s TriOx process.

The Results:

  • Confirmatory soil and groundwater samples following injections met applicable guidelines
  • Very short timeframe of treatment events
  • Combinations of soil and groundwater treatment simultaneously resulted in >90% contaminant reduction
Contact Trium Environmental

Speak with Our Experts

Contact Us

More Case Studies